Master Document and Delivery List
|
||
|
|
#################################
|
||
|
|
|
||
|
|
The MDDL is a comprehensive, hierarchical catalog of all the documents and files
|
||
|
|
related to the test reactor project. The MDDL includes information such as
|
||
|
|
document number, revision, title, and maturity status (e.g., completion
|
||
|
|
percentage). This serves as a central reference point, providing an overview of
|
||
|
|
the project's documentation and helping team members find relevant and
|
||
|
|
up-to-date information. Furthermore, the MDDL helps maintain organization,
|
||
|
|
control, and versioning of documents.
|
||
|
|
|
||
|
|
* Program Deliverables
|
||
|
|
* Full set of QA program procedures, including engineering and
|
||
|
|
configuration management
|
||
|
|
|
||
|
|
* Design Deliverables
|
||
|
|
* Design basis events and plant functions
|
||
|
|
* System Design Documents for all systems (including requirements/functions,
|
||
|
|
equipment list, parameters)
|
||
|
|
* Long-lead equipment list
|
||
|
|
* Probabilistic Risk Assessment (PRA) model
|
||
|
|
* General arrangement (3D model and extracted drawings)
|
||
|
|
* P&ID drawings for all systems
|
||
|
|
* Engineering simulator software
|
||
|
|
* Training simulator software
|
||
|
|
* Plant safety model (i.e. RELAP)
|
||
|
|
* Core models (i.e. CASMO/SIMULATE)
|
||
|
|
* Shielding models (i.e. MCNP)
|
||
|
|
* Balance of plant model (i.e. Flownex)
|
||
|
|
* Fuel performance models (i.e. FRAPCON and FRAPTRAN)
|
||
|
|
* Pipe restraint models
|
||
|
|
* Equipment models (i.e. SolidWorks)
|
||
|
|
* Civil/structural models, coupled to ship motions (i.e. ANSYS)
|
||
|
|
* Emergency planning documents
|
||
|
|
* Plant Technical Specifications
|
||
|
|
* Plant Operating Procedures
|
||
|
|
|
||
|
|
* Project Management Deliverables
|
||
|
|
* Resource-loaded schedule out to TTP operation
|
||
|
|
* Bottoms-up parametric cost estimate model and reports
|
||
|
|
|
||
|
|
* Regulatory Submittals
|
||
|
|
* Topical Reports
|
||
|
|
* Argument that Ship is the site (and so construction can occur before CP)
|
||
|
|
* Argument that TTP is a prototype reactor (104 license option)
|
||
|
|
* Argument
|
||
|
|
* Construction Permit Application
|
||
|
|
* Preliminary Safety Analysis Reports
|
||
|
|
* Environment Report
|
||
|
|
* Operating Permit Application
|