documents/requirements/industry/epri_alwr_urd.rst
Normal file
26
documents/requirements/industry/epri_alwr_urd.rst
Normal file
|
|
@ -0,0 +1,26 @@
|
|||
EPRI ALWR
|
||||
=========
|
||||
|
||||
This page contains some high-level requirements sourced from the EPRI Advanced
|
||||
Light Water Reactor Utility Requirements Document :cite:p:`mprAdvancedLightWater99a`
|
||||
|
||||
.. req:: Passive ALWRs shall not require safety-related AC electric power other than
|
||||
inverter supplied AC power for I&C.
|
||||
:id: R_ALWR_1
|
||||
|
||||
.. req:: 72-hours without manual operator action.
|
||||
:id: R_ALWR_2
|
||||
|
||||
For transients and accidents analyzed under the initiating event plus
|
||||
single failure Licensing Design Basis assumptions (which include loss of all ac
|
||||
power), no credit for manual operator action shall be necessary to meet core
|
||||
protection regulatory limits for at least 72 hours following initial indication
|
||||
of the need for action (i.e., approximately the time of the initiating event).
|
||||
|
||||
.. req:: Only simple actions and assistance shall be necessary beyond 72 hours
|
||||
:id: R_ALWR_3
|
||||
|
||||
.. req:: Off-site dose limits shall be maintained for at least 72 hours without
|
||||
the need for off-site assistance.
|
||||