diff --git a/documents/_data/schedule.yaml b/documents/_data/schedule.yaml index 21740b0..3413595 100644 --- a/documents/_data/schedule.yaml +++ b/documents/_data/schedule.yaml @@ -1,138 +1,193 @@ -lanes: - - name: "TTP" - color: "#1f77b4" - tasks: - - name: "Ship Design Cycle 1" - duration_days: 120 - predecessors: [RX0] - id: TTP1 - - name: "Nuke-Ready Guide" - milestone: true - predecessors: [TTP1] - - name: "Ship Design Cycle 2" - id: TTP2 - predecessors: [TTP1, RX1] - duration_days: 120 - - name: "RFI (non-stealth)" - milestone: true - predecessors: [TTP2] - - name: "Ship Design Cycle 3" - id: TTP3 - predecessors: [TTP2] - duration_days: 120 - - name: "RFP" - milestone: true - predecessors: [TTP3] - - name: "Evaluate Proposals" - id: TTP4 - duration_days: 90 - predecessors: [TTP3] - - name: "Ship Award" - milestone: true - predecessors: [TTP4] - - name: "Detailed Design & Construction" - id: TTP5 - duration_days: 900 - predecessors: [TTP4] - - name: "TTP Ship Delivery" - milestone: true - predecessors: [TTP5] - - name: "Test/Trials/Acceptance" - id: TTP6 - duration_days: 90 - predecessors: [TTP5] - - name: "Transit to Homeport" - id: TTP7 - duration_days: 30 - predecessors: [TTP6] - - name: "NEPP Integration" - id: TTP8 - duration_days: 60 - predecessors: [TTP7, RX5, SY7] - - name: "Hot plant testing" - id: TTP9 - duration_days: 180 - predecessors: [TTP8, SY7] +- name: "TTP" + color: "#1f77b4" + tasks: + - name: "Ship Design Cycle 1" + duration_days: 120 + predecessors: + - id: RX0 + id: TTP1 + - name: "Nuke-Ready Guide" + is_milestone: true + predecessors: + - id: TTP1 + - name: "Ship Design Cycle 2" + id: TTP2 + predecessors: + - id: TTP1 + - id: RX1 + duration_days: 120 + - name: "RFI (non-stealth)" + is_milestone: true + predecessors: + - id: TTP2 + - name: "Ship Design Cycle 3" + id: TTP3 + predecessors: + - id: TTP2 + duration_days: 120 + - name: "RFP" + is_milestone: true + predecessors: + - id: TTP3 + - name: "Evaluate Proposals" + id: TTP4 + duration_days: 90 + predecessors: + - id: TTP3 + - name: "Ship Award" + is_milestone: true + predecessors: + - id: TTP4 + - name: "Detailed Design & Construction" + id: TTP5 + duration_days: 900 + predecessors: + - id: TTP4 + - name: "TTP Ship Delivery" + is_milestone: true + predecessors: + - id: TTP5 + - name: "Test/Trials/Acceptance" + id: TTP6 + duration_days: 90 + predecessors: + - id: TTP5 + - name: "Transit to Homeport" + id: TTP7 + duration_days: 30 + predecessors: + - id: TTP6 + - name: "NEPP Integration" + id: TTP8 + duration_days: 60 + predecessors: + - id: TTP7 + - id: RX5 + - id: SY7 + - name: "Hot plant testing" + id: TTP9 + duration_days: 180 + predecessors: + - id: TTP8 + - id: SY7 - - name: "Shipyard" - color: "#ff7f0e" - tasks: - - name: "Shipyard conceptual design" - id: SY1 - start: 2026-01-01 - duration_days: 120 - predecessors: [RX0] - - name: "Real Estate Purchase" - id: SY2 - predecessors: [SY1] - duration_days: 270 - - name: "Shipyard Design Ph 1" - duration_days: 540 - id: SY3 - predecessors: [SY1, RX1] - - name: "Regulatory review" - duration_days: 270 - id: SY4 - predecessors: [SY1] - - name: "Reg Approval 1" - milestone: true - predecessors: [SY4] - - name: "Shipyard Design Ph 2" - id: SY5 - duration_days: 365 - predecessors: [SY3] - - name: "Reg Approval 2" - milestone: true - predecessors: [SY5] - - name: "Shipyard Construction Ph 1" - id: SY6 - duration_days: 635 - predecessors: [SY2] - - name: "Shipyard License" - milestone: true - predecessors: [SY6] - - name: "Shipyard Construction Ph 2" - id: SY7 - duration_days: 270 - predecessors: [SY6] +- name: "Shipyard" + color: "#ff7f0e" + tasks: + - name: "Shipyard conceptual design" + id: SY1 + start: 2026-01-01 + duration_days: 120 + predecessors: + - id: RX0 + - name: "Real Estate Purchase" + id: SY2 + predecessors: + - id: SY1 + duration_days: 270 + - name: "Shipyard Design Ph 1" + duration_days: 540 + id: SY3 + predecessors: + - id: SY1 + - id: RX1 + - name: "Regulatory review" + duration_days: 270 + id: SY4 + predecessors: + - id: SY1 + - name: "Reg Approval 1" + is_milestone: true + predecessors: + - id: SY4 + - name: "Shipyard Design Ph 2" + id: SY5 + duration_days: 365 + predecessors: + - id: SY3 + - name: "Reg Approval 2" + is_milestone: true + predecessors: + - id: SY5 + - name: "Shipyard Construction Ph 1" + id: SY6 + duration_days: 635 + predecessors: + - id: SY2 + - name: "Shipyard License" + is_milestone: true + predecessors: + - id: SY6 + - name: "Shipyard Construction Ph 2" + id: SY7 + duration_days: 270 + predecessors: + - id: SY6 - - name: "Reactor" - color: "#2ca02c" - tasks: - - name: "Rx concept design cycle 1" - id: RX0 - duration_days: 50 - - name: "Rx concept design cycle 2" - id: RX1 - duration_days: 100 - predecessors: [RX0] - - name: "Rx concept design cycle 3" - id: RX15 - duration_days: 300 - predecessors: [RX1] - - name: "Reactor prelim design" - id: RX2 - duration_days: 450 - predecessors: [RX15] - - name: "Submit License Application" - milestone: true - predecessors: [RX2] - - name: "Licensing review" - id: RX3 - duration_days: 450 - predecessors: [RX2] - - name: "Reactor detailed design" - id: RX4 - duration_days: 540 - predecessors: [RX2] - - name: "Receive Construction Permit" - milestone: true - predecessors: [RX3] - - name: "Reactor manufacturing" - id: RX5 - duration_days: 540 - predecessors: [RX3] - - name: "Receive Operating License" - milestone: true - predecessors: [RX5, TTP9] +- name: "Reactor" + color: "#2ca02c" + tasks: + - name: "Rx concept design cycle 1" + id: RX0 + duration_days: 50 + - name: "Rx concept design cycle 2" + id: RX1 + duration_days: 100 + predecessors: + - id: RX0 + - name: "Rx concept design cycle 3" + id: RX15 + duration_days: 300 + predecessors: + - id: RX1 + - name: "Reactor prelim design" + id: RX2 + duration_days: 360 + predecessors: + - id: RX15 + - name: "Reactor detailed design" + id: RX4 + duration_days: 500 + predecessors: + - id: RX2 + - name: "Reactor manufacturing" + id: RX5 + duration_days: 480 + predecessors: + - id: RX3 +- name: "Reactor License" + tasks: + - name: "Pre-licensing activities" + predecessors: + - id: RX1 + - id: RX15 + type: FF + duration_days: 450 + id: LI1 + - name: "Submit Construction Permit Application" + is_milestone: true + predecessors: + - id: RX2 + - id: LI1 + - name: "CP review by NRC" + id: RX3 + duration_days: 450 + predecessors: + - id: RX2 + - name: "Receive Construction Permit" + is_milestone: true + predecessors: + - id: RX3 + - name: "OL review by NRC" + # TODO: should end at end of hot plant testing + predecessors: + - id: RX4 + duration_days: 365 + - name: "Receive Operating License" + is_milestone: true + predecessors: + - id: RX5 + - id: TTP9 +# - name: "Fuel Handling License" +# tasks diff --git a/documents/project/index.rst b/documents/project/index.rst index b4023bf..cc2a09b 100644 --- a/documents/project/index.rst +++ b/documents/project/index.rst @@ -1,3 +1,5 @@ +.. _projects: + ################## Project Management ################## diff --git a/documents/project/mddl.rst b/documents/project/mddl.rst new file mode 100644 index 0000000..dcc6577 --- /dev/null +++ b/documents/project/mddl.rst @@ -0,0 +1,50 @@ +Master Document and Delivery List +################################# + +The MDDL is a comprehensive, hierarchical catalog of all the documents and files +related to the test reactor project. The MDDL includes information such as +document number, revision, title, and maturity status (e.g., completion +percentage). This serves as a central reference point, providing an overview of +the project's documentation and helping team members find relevant and +up-to-date information. Furthermore, the MDDL helps maintain organization, +control, and versioning of documents. + +* Program Deliverables + * Full set of QA program procedures, including engineering and + configuration management + +* Design Deliverables + * Design basis events and plant functions + * System Design Documents for all systems (including requirements/functions, + equipment list, parameters) + * Long-lead equipment list + * Probabilistic Risk Assessment (PRA) model + * General arrangement (3D model and extracted drawings) + * P&ID drawings for all systems + * Engineering simulator software + * Training simulator software + * Plant safety model (i.e. RELAP) + * Core models (i.e. CASMO/SIMULATE) + * Shielding models (i.e. MCNP) + * Balance of plant model (i.e. Flownex) + * Fuel performance models (i.e. FRAPCON and FRAPTRAN) + * Pipe restraint models + * Equipment models (i.e. SolidWorks) + * Civil/structural models, coupled to ship motions (i.e. ANSYS) + * Emergency planning documents + * Plant Technical Specifications + * Plant Operating Procedures + +* Project Management Deliverables + * Resource-loaded schedule out to TTP operation + * Bottoms-up parametric cost estimate model and reports + +* Regulatory Submittals + * Topical Reports + * Argument that Ship is the site (and so construction can occur before CP) + * Argument that TTP is a prototype reactor (104 license option) + * Argument + * Construction Permit Application + * Preliminary Safety Analysis Reports + * Environment Report + * Operating Permit Application \ No newline at end of file diff --git a/documents/project/projects.yaml b/documents/project/projects.yaml new file mode 100644 index 0000000..30382ae --- /dev/null +++ b/documents/project/projects.yaml @@ -0,0 +1,20 @@ +# Data regarding the various project the company is working on. +# The abbreviations drive document/record numbering +projects: + - name: Training and Test Platform + abbrev: TTP + description: > + The FOAK AMS nuclear ship, owned and operated by AMS and used for training and testing. + Effectively it produces the information validating the commercial readiness of + higher-powered ships. It's intended to be of the same design as the commercial + power plant, but may be downrated e.g. from 50 MWe to 10 MWe. + - name: Integration Shipyard + abbrev: ISH + description: > + The shipyard that integrates nuclear power plants into pre-built ships. + - name: Nuclear Ready + abbrev: NRDY + description: > + Standard interfacing information that defines how to make a ship that can + easily be outfitted with a nuclear power system at the Integration + Shipyard.