- name: "TTP" color: "#1f77b4" tasks: - name: "Ship Design Cycle 1" duration_days: 120 predecessors: - id: RX0 id: TTP1 - name: "Nuke-Ready Guide" is_milestone: true predecessors: - id: TTP1 - name: "Ship Design Cycle 2" id: TTP2 predecessors: - id: TTP1 - id: RX1 duration_days: 120 - name: "RFI (non-stealth)" is_milestone: true predecessors: - id: TTP2 - name: "Ship Design Cycle 3" id: TTP3 predecessors: - id: TTP2 duration_days: 120 - name: "RFP" is_milestone: true predecessors: - id: TTP3 - name: "Evaluate Proposals" id: TTP4 duration_days: 90 predecessors: - id: TTP3 - name: "Ship Award" is_milestone: true predecessors: - id: TTP4 - name: "Detailed Design & Construction" id: TTP5 duration_days: 900 predecessors: - id: TTP4 - name: "TTP Ship Delivery" is_milestone: true predecessors: - id: TTP5 - name: "Test/Trials/Acceptance" id: TTP6 duration_days: 90 predecessors: - id: TTP5 - name: "Transit to Homeport" id: TTP7 duration_days: 30 predecessors: - id: TTP6 - name: "NEPP Integration" id: TTP8 duration_days: 60 predecessors: - id: TTP7 - id: RX5 - id: SY7 - name: "Hot plant testing" id: TTP9 duration_days: 180 predecessors: - id: TTP8 - id: SY7 - name: "Shipyard" color: "#ff7f0e" tasks: - name: "Shipyard conceptual design" id: SY1 start: 2026-01-01 duration_days: 120 predecessors: - id: RX0 - name: "Real Estate Purchase" id: SY2 predecessors: - id: SY1 duration_days: 270 - name: "Shipyard Design Ph 1" duration_days: 540 id: SY3 predecessors: - id: SY1 - id: RX1 - name: "Regulatory review" duration_days: 270 id: SY4 predecessors: - id: SY1 - name: "Reg Approval 1" is_milestone: true predecessors: - id: SY4 - name: "Shipyard Design Ph 2" id: SY5 duration_days: 365 predecessors: - id: SY3 - name: "Reg Approval 2" is_milestone: true predecessors: - id: SY5 - name: "Shipyard Construction Ph 1" id: SY6 duration_days: 635 predecessors: - id: SY2 - name: "Shipyard License" is_milestone: true predecessors: - id: SY6 - name: "Shipyard Construction Ph 2" id: SY7 duration_days: 270 predecessors: - id: SY6 - name: "Reactor" color: "#2ca02c" tasks: - name: "Rx concept design cycle 1" id: RX0 duration_days: 50 - name: "Rx concept design cycle 2" id: RX1 duration_days: 100 predecessors: - id: RX0 - name: "Rx concept design cycle 3" id: RX15 duration_days: 300 predecessors: - id: RX1 - name: "Reactor prelim design" id: RX2 duration_days: 360 predecessors: - id: RX15 - name: "Reactor detailed design" id: RX4 duration_days: 500 predecessors: - id: RX2 - name: "Reactor manufacturing" id: RX5 duration_days: 480 predecessors: - id: RX3 - name: "Reactor License" tasks: - name: "Pre-licensing activities" predecessors: - id: RX1 - id: RX15 type: FF duration_days: 450 id: LI1 - name: "Submit Construction Permit Application" is_milestone: true predecessors: - id: RX2 - id: LI1 - name: "CP review by NRC" id: RX3 duration_days: 450 predecessors: - id: RX2 - name: "Receive Construction Permit" is_milestone: true predecessors: - id: RX3 - name: "OL review by NRC" # TODO: should end at end of hot plant testing predecessors: - id: RX4 duration_days: 365 - name: "Receive Operating License" is_milestone: true predecessors: - id: RX5 - id: TTP9 # - name: "Fuel Handling License" # tasks