lanes:
|
|
- name: "TTP"
|
|
color: "#1f77b4"
|
|
tasks:
|
|
- name: "Ship Design Cycle 1"
|
|
duration_days: 120
|
|
predecessors: [RX0]
|
|
id: TTP1
|
|
- name: "Nuke-Ready Guide"
|
|
milestone: true
|
|
predecessors: [TTP1]
|
|
- name: "Ship Design Cycle 2"
|
|
id: TTP2
|
|
predecessors: [TTP1, RX1]
|
|
duration_days: 120
|
|
- name: "RFI (non-stealth)"
|
|
milestone: true
|
|
predecessors: [TTP2]
|
|
- name: "Ship Design Cycle 3"
|
|
id: TTP3
|
|
predecessors: [TTP2]
|
|
duration_days: 120
|
|
- name: "RFP"
|
|
milestone: true
|
|
predecessors: [TTP3]
|
|
- name: "Evaluate Proposals"
|
|
id: TTP4
|
|
duration_days: 90
|
|
predecessors: [TTP3]
|
|
- name: "Ship Award"
|
|
milestone: true
|
|
predecessors: [TTP4]
|
|
- name: "Detailed Design & Construction"
|
|
id: TTP5
|
|
duration_days: 900
|
|
predecessors: [TTP4]
|
|
- name: "TTP Ship Delivery"
|
|
milestone: true
|
|
predecessors: [TTP5]
|
|
- name: "Test/Trials/Acceptance"
|
|
id: TTP6
|
|
duration_days: 90
|
|
predecessors: [TTP5]
|
|
- name: "Transit to Homeport"
|
|
id: TTP7
|
|
duration_days: 30
|
|
predecessors: [TTP6]
|
|
- name: "NEPP Integration"
|
|
id: TTP8
|
|
duration_days: 60
|
|
predecessors: [TTP7, RX5, SY7]
|
|
- name: "Hot plant testing"
|
|
id: TTP9
|
|
duration_days: 180
|
|
predecessors: [TTP8, SY7]
|
|
|
|
- name: "Shipyard"
|
|
color: "#ff7f0e"
|
|
tasks:
|
|
- name: "Shipyard conceptual design"
|
|
id: SY1
|
|
start: 2026-01-01
|
|
duration_days: 120
|
|
predecessors: [RX0]
|
|
- name: "Real Estate Purchase"
|
|
id: SY2
|
|
predecessors: [SY1]
|
|
duration_days: 270
|
|
- name: "Shipyard Design Ph 1"
|
|
duration_days: 540
|
|
id: SY3
|
|
predecessors: [SY1, RX1]
|
|
- name: "Regulatory review"
|
|
duration_days: 270
|
|
id: SY4
|
|
predecessors: [SY1]
|
|
- name: "Reg Approval 1"
|
|
milestone: true
|
|
predecessors: [SY4]
|
|
- name: "Shipyard Design Ph 2"
|
|
id: SY5
|
|
duration_days: 365
|
|
predecessors: [SY3]
|
|
- name: "Reg Approval 2"
|
|
milestone: true
|
|
predecessors: [SY5]
|
|
- name: "Shipyard Construction Ph 1"
|
|
id: SY6
|
|
duration_days: 635
|
|
predecessors: [SY2]
|
|
- name: "Shipyard License"
|
|
milestone: true
|
|
predecessors: [SY6]
|
|
- name: "Shipyard Construction Ph 2"
|
|
id: SY7
|
|
duration_days: 270
|
|
predecessors: [SY6]
|
|
|
|
- name: "Reactor"
|
|
color: "#2ca02c"
|
|
tasks:
|
|
- name: "Rx concept design cycle 1"
|
|
id: RX0
|
|
duration_days: 50
|
|
- name: "Rx concept design cycle 2"
|
|
id: RX1
|
|
duration_days: 100
|
|
predecessors: [RX0]
|
|
- name: "Rx concept design cycle 3"
|
|
id: RX15
|
|
duration_days: 300
|
|
predecessors: [RX1]
|
|
- name: "Reactor prelim design"
|
|
id: RX2
|
|
duration_days: 450
|
|
predecessors: [RX15]
|
|
- name: "Submit License Application"
|
|
milestone: true
|
|
predecessors: [RX2]
|
|
- name: "Licensing review"
|
|
id: RX3
|
|
duration_days: 450
|
|
predecessors: [RX2]
|
|
- name: "Reactor detailed design"
|
|
id: RX4
|
|
duration_days: 540
|
|
predecessors: [RX2]
|
|
- name: "Receive Construction Permit"
|
|
milestone: true
|
|
predecessors: [RX3]
|
|
- name: "Reactor manufacturing"
|
|
id: RX5
|
|
duration_days: 540
|
|
predecessors: [RX3]
|
|
- name: "Receive Operating License"
|
|
milestone: true
|
|
predecessors: [RX5, TTP9]
|
|
|