lanes:
- name: "TTP"
color: "#1f77b4"
tasks:
- name: "Ship Design Cycle 1"
duration_days: 120
predecessors: [RX0]
id: TTP1
- name: "Nuke-Ready Guide"
milestone: true
predecessors: [TTP1]
- name: "Ship Design Cycle 2"
id: TTP2
predecessors: [TTP1, RX1]
duration_days: 120
- name: "RFI (non-stealth)"
milestone: true
predecessors: [TTP2]
- name: "Ship Design Cycle 3"
id: TTP3
predecessors: [TTP2]
duration_days: 120
- name: "RFP"
milestone: true
predecessors: [TTP3]
- name: "Evaluate Proposals"
id: TTP4
duration_days: 90
predecessors: [TTP3]
- name: "Ship Award"
milestone: true
predecessors: [TTP4]
- name: "Detailed Design & Construction"
id: TTP5
duration_days: 900
predecessors: [TTP4]
- name: "TTP Ship Delivery"
milestone: true
predecessors: [TTP5]
- name: "Test/Trials/Acceptance"
id: TTP6
duration_days: 90
predecessors: [TTP5]
- name: "Transit to Homeport"
id: TTP7
duration_days: 30
predecessors: [TTP6]
- name: "NEPP Integration"
id: TTP8
duration_days: 60
predecessors: [TTP7, RX5, SY7]
- name: "Hot plant testing"
id: TTP9
duration_days: 180
predecessors: [TTP8, SY7]
- name: "Shipyard"
color: "#ff7f0e"
tasks:
- name: "Shipyard conceptual design"
id: SY1
start: 2026-01-01
duration_days: 120
predecessors: [RX0]
- name: "Real Estate Purchase"
id: SY2
predecessors: [SY1]
duration_days: 270
- name: "Shipyard Design Ph 1"
duration_days: 540
id: SY3
predecessors: [SY1, RX1]
- name: "Regulatory review"
duration_days: 270
id: SY4
predecessors: [SY1]
- name: "Reg Approval 1"
milestone: true
predecessors: [SY4]
- name: "Shipyard Design Ph 2"
id: SY5
duration_days: 365
predecessors: [SY3]
- name: "Reg Approval 2"
milestone: true
predecessors: [SY5]
- name: "Shipyard Construction Ph 1"
id: SY6
duration_days: 635
predecessors: [SY2]
- name: "Shipyard License"
milestone: true
predecessors: [SY6]
- name: "Shipyard Construction Ph 2"
id: SY7
duration_days: 270
predecessors: [SY6]
- name: "Reactor"
color: "#2ca02c"
tasks:
- name: "Rx concept design cycle 1"
id: RX0
duration_days: 50
- name: "Rx concept design cycle 2"
id: RX1
duration_days: 100
predecessors: [RX0]
- name: "Rx concept design cycle 3"
id: RX15
duration_days: 300
predecessors: [RX1]
- name: "Reactor prelim design"
id: RX2
duration_days: 450
predecessors: [RX15]
- name: "Submit License Application"
milestone: true
predecessors: [RX2]
- name: "Licensing review"
id: RX3
duration_days: 450
predecessors: [RX2]
- name: "Reactor detailed design"
id: RX4
duration_days: 540
predecessors: [RX2]
- name: "Receive Construction Permit"
milestone: true
predecessors: [RX3]
- name: "Reactor manufacturing"
id: RX5
duration_days: 540
predecessors: [RX3]
- name: "Receive Operating License"
milestone: true
predecessors: [RX5, TTP9]