- name: "TTP"
color: "#1f77b4"
tasks:
- name: "Ship Design Cycle 1"
duration_days: 120
predecessors:
- id: RX0
id: TTP1
- name: "Nuke-Ready Guide"
is_milestone: true
predecessors:
- id: TTP1
- name: "Ship Design Cycle 2"
id: TTP2
predecessors:
- id: TTP1
- id: RX1
duration_days: 120
- name: "RFI (non-stealth)"
is_milestone: true
predecessors:
- id: TTP2
- name: "Ship Design Cycle 3"
id: TTP3
predecessors:
- id: TTP2
duration_days: 120
- name: "RFP"
is_milestone: true
predecessors:
- id: TTP3
- name: "Evaluate Proposals"
id: TTP4
duration_days: 90
predecessors:
- id: TTP3
- name: "Ship Award"
is_milestone: true
predecessors:
- id: TTP4
- name: "Detailed Design & Construction"
id: TTP5
duration_days: 900
predecessors:
- id: TTP4
- name: "TTP Ship Delivery"
is_milestone: true
predecessors:
- id: TTP5
- name: "Test/Trials/Acceptance"
id: TTP6
duration_days: 90
predecessors:
- id: TTP5
- name: "Transit to Homeport"
id: TTP7
duration_days: 30
predecessors:
- id: TTP6
- name: "NEPP Integration"
id: TTP8
duration_days: 60
predecessors:
- id: TTP7
- id: RX5
- id: SY7
- name: "Hot plant testing"
id: TTP9
duration_days: 180
predecessors:
- id: TTP8
- id: SY7
- name: "Shipyard"
color: "#ff7f0e"
tasks:
- name: "Shipyard conceptual design"
id: SY1
start: 2026-01-01
duration_days: 120
predecessors:
- id: RX0
- name: "Real Estate Purchase"
id: SY2
predecessors:
- id: SY1
duration_days: 270
- name: "Shipyard Design Ph 1"
duration_days: 540
id: SY3
predecessors:
- id: SY1
- id: RX1
- name: "Regulatory review"
duration_days: 270
id: SY4
predecessors:
- id: SY1
- name: "Reg Approval 1"
is_milestone: true
predecessors:
- id: SY4
- name: "Shipyard Design Ph 2"
id: SY5
duration_days: 365
predecessors:
- id: SY3
- name: "Reg Approval 2"
is_milestone: true
predecessors:
- id: SY5
- name: "Shipyard Construction Ph 1"
id: SY6
duration_days: 635
predecessors:
- id: SY2
- name: "Shipyard License"
is_milestone: true
predecessors:
- id: SY6
- name: "Shipyard Construction Ph 2"
id: SY7
duration_days: 270
predecessors:
- id: SY6
- name: "Reactor"
color: "#2ca02c"
tasks:
- name: "Rx concept design cycle 1"
id: RX0
duration_days: 50
- name: "Rx concept design cycle 2"
id: RX1
duration_days: 100
predecessors:
- id: RX0
- name: "Rx concept design cycle 3"
id: RX15
duration_days: 300
predecessors:
- id: RX1
- name: "Reactor prelim design"
id: RX2
duration_days: 360
predecessors:
- id: RX15
- name: "Reactor detailed design"
id: RX4
duration_days: 500
predecessors:
- id: RX2
- name: "Reactor manufacturing"
id: RX5
duration_days: 480
predecessors:
- id: RX3
- name: "Reactor License"
tasks:
- name: "Pre-licensing activities"
predecessors:
- id: RX1
- id: RX15
type: FF
duration_days: 450
id: LI1
- name: "Submit Construction Permit Application"
is_milestone: true
predecessors:
- id: RX2
- id: LI1
- name: "CP review by NRC"
id: RX3
duration_days: 450
predecessors:
- id: RX2
- name: "Receive Construction Permit"
is_milestone: true
predecessors:
- id: RX3
- name: "OL review by NRC"
# TODO: should end at end of hot plant testing
predecessors:
- id: RX4
duration_days: 365
- name: "Receive Operating License"
is_milestone: true
predecessors:
- id: RX5
- id: TTP9
# - name: "Fuel Handling License"
# tasks