- name: "TTP"
|
|
color: "#1f77b4"
|
|
tasks:
|
|
- name: "Ship Design Cycle 1"
|
|
duration_days: 120
|
|
predecessors:
|
|
- id: RX0
|
|
id: TTP1
|
|
- name: "Nuke-Ready Guide"
|
|
is_milestone: true
|
|
predecessors:
|
|
- id: TTP1
|
|
- name: "Ship Design Cycle 2"
|
|
id: TTP2
|
|
predecessors:
|
|
- id: TTP1
|
|
- id: RX1
|
|
duration_days: 120
|
|
- name: "RFI (non-stealth)"
|
|
is_milestone: true
|
|
predecessors:
|
|
- id: TTP2
|
|
- name: "Ship Design Cycle 3"
|
|
id: TTP3
|
|
predecessors:
|
|
- id: TTP2
|
|
duration_days: 120
|
|
- name: "RFP"
|
|
is_milestone: true
|
|
predecessors:
|
|
- id: TTP3
|
|
- name: "Evaluate Proposals"
|
|
id: TTP4
|
|
duration_days: 90
|
|
predecessors:
|
|
- id: TTP3
|
|
- name: "Ship Award"
|
|
is_milestone: true
|
|
predecessors:
|
|
- id: TTP4
|
|
- name: "Detailed Design & Construction"
|
|
id: TTP5
|
|
duration_days: 900
|
|
predecessors:
|
|
- id: TTP4
|
|
- name: "TTP Ship Delivery"
|
|
is_milestone: true
|
|
predecessors:
|
|
- id: TTP5
|
|
- name: "Test/Trials/Acceptance"
|
|
id: TTP6
|
|
duration_days: 90
|
|
predecessors:
|
|
- id: TTP5
|
|
- name: "Transit to Homeport"
|
|
id: TTP7
|
|
duration_days: 30
|
|
predecessors:
|
|
- id: TTP6
|
|
- name: "NEPP Integration"
|
|
id: TTP8
|
|
duration_days: 60
|
|
predecessors:
|
|
- id: TTP7
|
|
- id: RX5
|
|
- id: SY7
|
|
- name: "Hot plant testing"
|
|
id: TTP9
|
|
duration_days: 180
|
|
predecessors:
|
|
- id: TTP8
|
|
- id: SY7
|
|
|
|
- name: "Shipyard"
|
|
color: "#ff7f0e"
|
|
tasks:
|
|
- name: "Shipyard conceptual design"
|
|
id: SY1
|
|
start: 2026-01-01
|
|
duration_days: 120
|
|
predecessors:
|
|
- id: RX0
|
|
- name: "Real Estate Purchase"
|
|
id: SY2
|
|
predecessors:
|
|
- id: SY1
|
|
duration_days: 270
|
|
- name: "Shipyard Design Ph 1"
|
|
duration_days: 540
|
|
id: SY3
|
|
predecessors:
|
|
- id: SY1
|
|
- id: RX1
|
|
- name: "Regulatory review"
|
|
duration_days: 270
|
|
id: SY4
|
|
predecessors:
|
|
- id: SY1
|
|
- name: "Reg Approval 1"
|
|
is_milestone: true
|
|
predecessors:
|
|
- id: SY4
|
|
- name: "Shipyard Design Ph 2"
|
|
id: SY5
|
|
duration_days: 365
|
|
predecessors:
|
|
- id: SY3
|
|
- name: "Reg Approval 2"
|
|
is_milestone: true
|
|
predecessors:
|
|
- id: SY5
|
|
- name: "Shipyard Construction Ph 1"
|
|
id: SY6
|
|
duration_days: 635
|
|
predecessors:
|
|
- id: SY2
|
|
- name: "Shipyard License"
|
|
is_milestone: true
|
|
predecessors:
|
|
- id: SY6
|
|
- name: "Shipyard Construction Ph 2"
|
|
id: SY7
|
|
duration_days: 270
|
|
predecessors:
|
|
- id: SY6
|
|
|
|
- name: "Reactor"
|
|
color: "#2ca02c"
|
|
tasks:
|
|
- name: "Rx concept design cycle 1"
|
|
id: RX0
|
|
duration_days: 50
|
|
- name: "Rx concept design cycle 2"
|
|
id: RX1
|
|
duration_days: 100
|
|
predecessors:
|
|
- id: RX0
|
|
- name: "Rx concept design cycle 3"
|
|
id: RX15
|
|
duration_days: 300
|
|
predecessors:
|
|
- id: RX1
|
|
- name: "Reactor prelim design"
|
|
id: RX2
|
|
duration_days: 360
|
|
predecessors:
|
|
- id: RX15
|
|
- name: "Reactor detailed design"
|
|
id: RX4
|
|
duration_days: 500
|
|
predecessors:
|
|
- id: RX2
|
|
- name: "Reactor manufacturing"
|
|
id: RX5
|
|
duration_days: 480
|
|
predecessors:
|
|
- id: RX3
|
|
|
|
- name: "Reactor License"
|
|
tasks:
|
|
- name: "Pre-licensing activities"
|
|
predecessors:
|
|
- id: RX1
|
|
- id: RX15
|
|
type: FF
|
|
duration_days: 450
|
|
id: LI1
|
|
- name: "Submit Construction Permit Application"
|
|
is_milestone: true
|
|
predecessors:
|
|
- id: RX2
|
|
- id: LI1
|
|
- name: "CP review by NRC"
|
|
id: RX3
|
|
duration_days: 450
|
|
predecessors:
|
|
- id: RX2
|
|
- name: "Receive Construction Permit"
|
|
is_milestone: true
|
|
predecessors:
|
|
- id: RX3
|
|
- name: "OL review by NRC"
|
|
# TODO: should end at end of hot plant testing
|
|
predecessors:
|
|
- id: RX4
|
|
duration_days: 365
|
|
- name: "Receive Operating License"
|
|
is_milestone: true
|
|
predecessors:
|
|
- id: RX5
|
|
- id: TTP9
|
|
# - name: "Fuel Handling License"
|
|
# tasks
|