Some AMS specific stuff, and plant work
This commit is contained in:
parent
9332337581
commit
e474c140ee
30 changed files with 558 additions and 21 deletions
16
documents/_data/plant-parameters.yaml
Normal file
16
documents/_data/plant-parameters.yaml
Normal file
|
|
@ -0,0 +1,16 @@
|
|||
- name: Power Range
|
||||
val_low: 0.750
|
||||
val_high: 16
|
||||
units: MWe
|
||||
req: R_AMS_1
|
||||
tags: [electrical]
|
||||
- name: Backbone Voltage
|
||||
val: 3.6
|
||||
units: kVAC
|
||||
req: R_AMS_2
|
||||
tags: [electrical]
|
||||
- name: Backbone Frequency
|
||||
val: 60
|
||||
units: Hz
|
||||
req: R_AMS_2
|
||||
tags: [electrical]
|
||||
138
documents/_data/schedule.yaml
Normal file
138
documents/_data/schedule.yaml
Normal file
|
|
@ -0,0 +1,138 @@
|
|||
lanes:
|
||||
- name: "TTP"
|
||||
color: "#1f77b4"
|
||||
tasks:
|
||||
- name: "Ship Design Cycle 1"
|
||||
duration_days: 120
|
||||
predecessors: [RX0]
|
||||
id: TTP1
|
||||
- name: "Nuke-Ready Guide"
|
||||
milestone: true
|
||||
predecessors: [TTP1]
|
||||
- name: "Ship Design Cycle 2"
|
||||
id: TTP2
|
||||
predecessors: [TTP1, RX1]
|
||||
duration_days: 120
|
||||
- name: "RFI (non-stealth)"
|
||||
milestone: true
|
||||
predecessors: [TTP2]
|
||||
- name: "Ship Design Cycle 3"
|
||||
id: TTP3
|
||||
predecessors: [TTP2]
|
||||
duration_days: 120
|
||||
- name: "RFP"
|
||||
milestone: true
|
||||
predecessors: [TTP3]
|
||||
- name: "Evaluate Proposals"
|
||||
id: TTP4
|
||||
duration_days: 90
|
||||
predecessors: [TTP3]
|
||||
- name: "Ship Award"
|
||||
milestone: true
|
||||
predecessors: [TTP4]
|
||||
- name: "Detailed Design & Construction"
|
||||
id: TTP5
|
||||
duration_days: 900
|
||||
predecessors: [TTP4]
|
||||
- name: "TTP Ship Delivery"
|
||||
milestone: true
|
||||
predecessors: [TTP5]
|
||||
- name: "Test/Trials/Acceptance"
|
||||
id: TTP6
|
||||
duration_days: 90
|
||||
predecessors: [TTP5]
|
||||
- name: "Transit to Homeport"
|
||||
id: TTP7
|
||||
duration_days: 30
|
||||
predecessors: [TTP6]
|
||||
- name: "NEPP Integration"
|
||||
id: TTP8
|
||||
duration_days: 60
|
||||
predecessors: [TTP7, RX5, SY7]
|
||||
- name: "Hot plant testing"
|
||||
id: TTP9
|
||||
duration_days: 180
|
||||
predecessors: [TTP8, SY7]
|
||||
|
||||
- name: "Shipyard"
|
||||
color: "#ff7f0e"
|
||||
tasks:
|
||||
- name: "Shipyard conceptual design"
|
||||
id: SY1
|
||||
start: 2026-01-01
|
||||
duration_days: 120
|
||||
predecessors: [RX0]
|
||||
- name: "Real Estate Purchase"
|
||||
id: SY2
|
||||
predecessors: [SY1]
|
||||
duration_days: 270
|
||||
- name: "Shipyard Design Ph 1"
|
||||
duration_days: 540
|
||||
id: SY3
|
||||
predecessors: [SY1, RX1]
|
||||
- name: "Regulatory review"
|
||||
duration_days: 270
|
||||
id: SY4
|
||||
predecessors: [SY1]
|
||||
- name: "Reg Approval 1"
|
||||
milestone: true
|
||||
predecessors: [SY4]
|
||||
- name: "Shipyard Design Ph 2"
|
||||
id: SY5
|
||||
duration_days: 365
|
||||
predecessors: [SY3]
|
||||
- name: "Reg Approval 2"
|
||||
milestone: true
|
||||
predecessors: [SY5]
|
||||
- name: "Shipyard Construction Ph 1"
|
||||
id: SY6
|
||||
duration_days: 635
|
||||
predecessors: [SY2]
|
||||
- name: "Shipyard License"
|
||||
milestone: true
|
||||
predecessors: [SY6]
|
||||
- name: "Shipyard Construction Ph 2"
|
||||
id: SY7
|
||||
duration_days: 270
|
||||
predecessors: [SY6]
|
||||
|
||||
- name: "Reactor"
|
||||
color: "#2ca02c"
|
||||
tasks:
|
||||
- name: "Rx concept design cycle 1"
|
||||
id: RX0
|
||||
duration_days: 50
|
||||
- name: "Rx concept design cycle 2"
|
||||
id: RX1
|
||||
duration_days: 100
|
||||
predecessors: [RX0]
|
||||
- name: "Rx concept design cycle 3"
|
||||
id: RX15
|
||||
duration_days: 300
|
||||
predecessors: [RX1]
|
||||
- name: "Reactor prelim design"
|
||||
id: RX2
|
||||
duration_days: 450
|
||||
predecessors: [RX15]
|
||||
- name: "Submit License Application"
|
||||
milestone: true
|
||||
predecessors: [RX2]
|
||||
- name: "Licensing review"
|
||||
id: RX3
|
||||
duration_days: 450
|
||||
predecessors: [RX2]
|
||||
- name: "Reactor detailed design"
|
||||
id: RX4
|
||||
duration_days: 540
|
||||
predecessors: [RX2]
|
||||
- name: "Receive Construction Permit"
|
||||
milestone: true
|
||||
predecessors: [RX3]
|
||||
- name: "Reactor manufacturing"
|
||||
id: RX5
|
||||
duration_days: 540
|
||||
predecessors: [RX3]
|
||||
- name: "Receive Operating License"
|
||||
milestone: true
|
||||
predecessors: [RX5, TTP9]
|
||||
|
||||