AMS: adjust schedule format

Add projects, add MDDL
This commit is contained in:
Nick Touran 2025-12-29 12:12:38 -05:00
parent f13e1e2ee2
commit f7ee72a66b
4 changed files with 262 additions and 135 deletions

View file

@ -1,138 +1,193 @@
lanes: - name: "TTP"
- name: "TTP" color: "#1f77b4"
color: "#1f77b4" tasks:
tasks: - name: "Ship Design Cycle 1"
- name: "Ship Design Cycle 1" duration_days: 120
duration_days: 120 predecessors:
predecessors: [RX0] - id: RX0
id: TTP1 id: TTP1
- name: "Nuke-Ready Guide" - name: "Nuke-Ready Guide"
milestone: true is_milestone: true
predecessors: [TTP1] predecessors:
- name: "Ship Design Cycle 2" - id: TTP1
id: TTP2 - name: "Ship Design Cycle 2"
predecessors: [TTP1, RX1] id: TTP2
duration_days: 120 predecessors:
- name: "RFI (non-stealth)" - id: TTP1
milestone: true - id: RX1
predecessors: [TTP2] duration_days: 120
- name: "Ship Design Cycle 3" - name: "RFI (non-stealth)"
id: TTP3 is_milestone: true
predecessors: [TTP2] predecessors:
duration_days: 120 - id: TTP2
- name: "RFP" - name: "Ship Design Cycle 3"
milestone: true id: TTP3
predecessors: [TTP3] predecessors:
- name: "Evaluate Proposals" - id: TTP2
id: TTP4 duration_days: 120
duration_days: 90 - name: "RFP"
predecessors: [TTP3] is_milestone: true
- name: "Ship Award" predecessors:
milestone: true - id: TTP3
predecessors: [TTP4] - name: "Evaluate Proposals"
- name: "Detailed Design & Construction" id: TTP4
id: TTP5 duration_days: 90
duration_days: 900 predecessors:
predecessors: [TTP4] - id: TTP3
- name: "TTP Ship Delivery" - name: "Ship Award"
milestone: true is_milestone: true
predecessors: [TTP5] predecessors:
- name: "Test/Trials/Acceptance" - id: TTP4
id: TTP6 - name: "Detailed Design & Construction"
duration_days: 90 id: TTP5
predecessors: [TTP5] duration_days: 900
- name: "Transit to Homeport" predecessors:
id: TTP7 - id: TTP4
duration_days: 30 - name: "TTP Ship Delivery"
predecessors: [TTP6] is_milestone: true
- name: "NEPP Integration" predecessors:
id: TTP8 - id: TTP5
duration_days: 60 - name: "Test/Trials/Acceptance"
predecessors: [TTP7, RX5, SY7] id: TTP6
- name: "Hot plant testing" duration_days: 90
id: TTP9 predecessors:
duration_days: 180 - id: TTP5
predecessors: [TTP8, SY7] - name: "Transit to Homeport"
id: TTP7
duration_days: 30
predecessors:
- id: TTP6
- name: "NEPP Integration"
id: TTP8
duration_days: 60
predecessors:
- id: TTP7
- id: RX5
- id: SY7
- name: "Hot plant testing"
id: TTP9
duration_days: 180
predecessors:
- id: TTP8
- id: SY7
- name: "Shipyard" - name: "Shipyard"
color: "#ff7f0e" color: "#ff7f0e"
tasks: tasks:
- name: "Shipyard conceptual design" - name: "Shipyard conceptual design"
id: SY1 id: SY1
start: 2026-01-01 start: 2026-01-01
duration_days: 120 duration_days: 120
predecessors: [RX0] predecessors:
- name: "Real Estate Purchase" - id: RX0
id: SY2 - name: "Real Estate Purchase"
predecessors: [SY1] id: SY2
duration_days: 270 predecessors:
- name: "Shipyard Design Ph 1" - id: SY1
duration_days: 540 duration_days: 270
id: SY3 - name: "Shipyard Design Ph 1"
predecessors: [SY1, RX1] duration_days: 540
- name: "Regulatory review" id: SY3
duration_days: 270 predecessors:
id: SY4 - id: SY1
predecessors: [SY1] - id: RX1
- name: "Reg Approval 1" - name: "Regulatory review"
milestone: true duration_days: 270
predecessors: [SY4] id: SY4
- name: "Shipyard Design Ph 2" predecessors:
id: SY5 - id: SY1
duration_days: 365 - name: "Reg Approval 1"
predecessors: [SY3] is_milestone: true
- name: "Reg Approval 2" predecessors:
milestone: true - id: SY4
predecessors: [SY5] - name: "Shipyard Design Ph 2"
- name: "Shipyard Construction Ph 1" id: SY5
id: SY6 duration_days: 365
duration_days: 635 predecessors:
predecessors: [SY2] - id: SY3
- name: "Shipyard License" - name: "Reg Approval 2"
milestone: true is_milestone: true
predecessors: [SY6] predecessors:
- name: "Shipyard Construction Ph 2" - id: SY5
id: SY7 - name: "Shipyard Construction Ph 1"
duration_days: 270 id: SY6
predecessors: [SY6] duration_days: 635
predecessors:
- id: SY2
- name: "Shipyard License"
is_milestone: true
predecessors:
- id: SY6
- name: "Shipyard Construction Ph 2"
id: SY7
duration_days: 270
predecessors:
- id: SY6
- name: "Reactor" - name: "Reactor"
color: "#2ca02c" color: "#2ca02c"
tasks: tasks:
- name: "Rx concept design cycle 1" - name: "Rx concept design cycle 1"
id: RX0 id: RX0
duration_days: 50 duration_days: 50
- name: "Rx concept design cycle 2" - name: "Rx concept design cycle 2"
id: RX1 id: RX1
duration_days: 100 duration_days: 100
predecessors: [RX0] predecessors:
- name: "Rx concept design cycle 3" - id: RX0
id: RX15 - name: "Rx concept design cycle 3"
duration_days: 300 id: RX15
predecessors: [RX1] duration_days: 300
- name: "Reactor prelim design" predecessors:
id: RX2 - id: RX1
duration_days: 450 - name: "Reactor prelim design"
predecessors: [RX15] id: RX2
- name: "Submit License Application" duration_days: 360
milestone: true predecessors:
predecessors: [RX2] - id: RX15
- name: "Licensing review" - name: "Reactor detailed design"
id: RX3 id: RX4
duration_days: 450 duration_days: 500
predecessors: [RX2] predecessors:
- name: "Reactor detailed design" - id: RX2
id: RX4 - name: "Reactor manufacturing"
duration_days: 540 id: RX5
predecessors: [RX2] duration_days: 480
- name: "Receive Construction Permit" predecessors:
milestone: true - id: RX3
predecessors: [RX3]
- name: "Reactor manufacturing"
id: RX5
duration_days: 540
predecessors: [RX3]
- name: "Receive Operating License"
milestone: true
predecessors: [RX5, TTP9]
- name: "Reactor License"
tasks:
- name: "Pre-licensing activities"
predecessors:
- id: RX1
- id: RX15
type: FF
duration_days: 450
id: LI1
- name: "Submit Construction Permit Application"
is_milestone: true
predecessors:
- id: RX2
- id: LI1
- name: "CP review by NRC"
id: RX3
duration_days: 450
predecessors:
- id: RX2
- name: "Receive Construction Permit"
is_milestone: true
predecessors:
- id: RX3
- name: "OL review by NRC"
# TODO: should end at end of hot plant testing
predecessors:
- id: RX4
duration_days: 365
- name: "Receive Operating License"
is_milestone: true
predecessors:
- id: RX5
- id: TTP9
# - name: "Fuel Handling License"
# tasks

View file

@ -1,3 +1,5 @@
.. _projects:
################## ##################
Project Management Project Management
################## ##################

View file

@ -0,0 +1,50 @@
Master Document and Delivery List
#################################
The MDDL is a comprehensive, hierarchical catalog of all the documents and files
related to the test reactor project. The MDDL includes information such as
document number, revision, title, and maturity status (e.g., completion
percentage). This serves as a central reference point, providing an overview of
the project's documentation and helping team members find relevant and
up-to-date information. Furthermore, the MDDL helps maintain organization,
control, and versioning of documents.
* Program Deliverables
* Full set of QA program procedures, including engineering and
configuration management
* Design Deliverables
* Design basis events and plant functions
* System Design Documents for all systems (including requirements/functions,
equipment list, parameters)
* Long-lead equipment list
* Probabilistic Risk Assessment (PRA) model
* General arrangement (3D model and extracted drawings)
* P&ID drawings for all systems
* Engineering simulator software
* Training simulator software
* Plant safety model (i.e. RELAP)
* Core models (i.e. CASMO/SIMULATE)
* Shielding models (i.e. MCNP)
* Balance of plant model (i.e. Flownex)
* Fuel performance models (i.e. FRAPCON and FRAPTRAN)
* Pipe restraint models
* Equipment models (i.e. SolidWorks)
* Civil/structural models, coupled to ship motions (i.e. ANSYS)
* Emergency planning documents
* Plant Technical Specifications
* Plant Operating Procedures
* Project Management Deliverables
* Resource-loaded schedule out to TTP operation
* Bottoms-up parametric cost estimate model and reports
* Regulatory Submittals
* Topical Reports
* Argument that Ship is the site (and so construction can occur before CP)
* Argument that TTP is a prototype reactor (104 license option)
* Argument
* Construction Permit Application
* Preliminary Safety Analysis Reports
* Environment Report
* Operating Permit Application

View file

@ -0,0 +1,20 @@
# Data regarding the various project the company is working on.
# The abbreviations drive document/record numbering
projects:
- name: Training and Test Platform
abbrev: TTP
description: >
The FOAK AMS nuclear ship, owned and operated by AMS and used for training and testing.
Effectively it produces the information validating the commercial readiness of
higher-powered ships. It's intended to be of the same design as the commercial
power plant, but may be downrated e.g. from 50 MWe to 10 MWe.
- name: Integration Shipyard
abbrev: ISH
description: >
The shipyard that integrates nuclear power plants into pre-built ships.
- name: Nuclear Ready
abbrev: NRDY
description: >
Standard interfacing information that defines how to make a ship that can
easily be outfitted with a nuclear power system at the Integration
Shipyard.